KONSEP NILAI HASIL (EARNED VALUE EVALUASI PENGENDALIAN WAKTU DAN BIAYA PADA PROYEK PENINGKATAN JALAN BOJONGSARI- MAJENANG KABUPATEN CILACAP DENGAN METODE KONSEP NILAI HASIL (EARNED VALUE CONCEPT)
DOI:
https://doi.org/10.25157/mediailmiahtekniksipil.v3i1.5509Kata Kunci:
Earned Value Concept, Control Time , Control CostAbstrak
Evaluation control time And costs in the Project Improvement Road Bojongsari-Majenang with use method Earned Value Concept. Methods used in study This is descriptive quantitative, research that describes condition project certain with analysis of existing data. Data analysis using method analytical And descriptive . Analytical means the data has been There is processed such appearance so that produce results the end that can concluded . While descriptive It means is with to expose problems that have been There is or visible . Earned Value Concept study trend variants timetable And variants cost on something period time during project ongoing . Results study show that that Earned Value Concept can control time And cost on Project Improvement Road Bojongsari – Majenang Regency Cilacap. The average SPI value is less from 1, p. This show that control time on Project Improvement Road Bojongsari-Majenang Regency Cilacap not enough good, because No capable achieve the work targets that have been set planned . Average Value CPI not enough from 1, p. This show cost control on Project Improvement Road Bojongsari-Majenang Regency Cilacap is bad, because the costs incurred are greater if compared to the value obtained or in other words there is waste costs , but on Sunday final implementation work Project Improvement Road Bojongsari – Majenang Regency Cilacap finished appropriate time And cost incurred in accordance with planned budget .